Vaishnavi AT-One Life Project Schedule

Featured Image of Vaishnavi AT-One Life Project Schedule


Vaishnavi AT-One Life Project Schedule runs from February 2022 to December 2027 across four phases. Phase I began in March 2022 and reached completion in March 2025. Phases II and III followed, finishing in May 2025 and June 2026. Phase IV started on 1 May 2026 and has a RERA completion date of 18 December 2027.

This page lays out the full schedule in one place, from plan approval to completion for every phase. It also explains how long each phase took and what the schedule means for your buying plans.

Full Project Schedule by Phase


The table below shows every key date for each phase, based on the project's RERA and approval records.

Milestone Phase I Phase II Phase III Phase IV
Plan approved 24 Feb 2022 25 Aug 2022 6 Jun 2024 19 Dec 2025
RERA registration 17 Mar 2022 20 Sep 2022 31 Aug 2024 13 May 2026
Work started 3 Mar 2022 25 Aug 2022 10 Jun 2024 1 May 2026
Completion date 3 Mar 2025 29 May 2025 5 Jun 2026 18 Dec 2027
Status Completed Completed Completed Ongoing

The Joint Development Agreement for the project was registered on 3 March 2022 at Devanahalli. This was the same day work began on Phase I.

How Long Each Phase Takes


Each phase follows its own schedule, based on its size and the work involved. Here is the planned time from start to completion for each one.

  • Phase I: about 36 months, from March 2022 to March 2025, for 523 plots on 39.12 acres.
  • Phase II: about 33 months, from August 2022 to May 2025, for 64 plots on 5.35 acres.
  • Phase III: about 24 months, from June 2024 to June 2026, for 85 plots on 5.77 acres.
  • Phase IV: about 20 months, from May 2026 to December 2027, for 227 plots on 16.12 acres.

The later phases follow shorter schedules, as the team builds on systems and experience from the earlier work.

The Schedule Pattern Explained


Vaishnavi Group has followed a clear pattern across the four phases. First, it gets the BIAAPA layout plan approved. Next, it registers the phase with Karnataka RERA and starts work. Then it builds the roads, drains, utility lines and parks within the RERA timeline.

This step-by-step approach keeps risk low for buyers. Each phase gets its own approvals, so a delay in one phase does not hold up another. It also lets the group show a finished phase before opening the next one.

Phase I and Phase II: The Early Schedule


Phase I was the starting point of the whole project. Its plan was approved on 24 February 2022, and work began on 3 March 2022. RERA registration followed on 17 March 2022, just before the official launch in April.

Phase II started only a few months later, on 25 August 2022. Both phases ran side by side for a while. Phase I reached completion on 3 March 2025, and Phase II followed on 29 May 2025.

Phase III and Phase IV: The Later Schedule


Phase III opened in mid-2024, with its plan approved on 6 June 2024. Work began on 10 June 2024, and RERA registration came on 31 August 2024. The phase reached its completion date on 5 June 2026.

Phase IV is the final phase on the current schedule. Its plan was approved on 19 December 2025, and work started on 1 May 2026. The phase registered with RERA in May 2026 and is due by 18 December 2027.

How Nearby Projects Fit the Schedule


The project schedule lines up well with major works around Devanahalli. These outside projects will shape how useful your plot becomes in the coming years.

Nearby Project Expected Timeline
Namma Metro Blue Line, Hebbal to airport Targeted for June 2027
Satellite Town Ring Road, Dobbaspet to Hoskote Open since March 2024
Kempegowda Airport capacity expansion Environmental clearance received

The airport metro stretch is due just months before Phase IV completion. So by Phase IV handover, metro access to the airport belt should be close.

What the Schedule Means for Buyers


The schedule helps you plan your purchase around your own needs. If you want to build soon, the completed phases give you a near-ready plot. If you want time to plan, Phase IV gives you a clear end date in late 2027.

Either way, ask the sales team how your payment plan links to the schedule. A payment plan that matches the work progress keeps your money safer.

FAQs


1. What is the overall schedule of Vaishnavi AT-One Life?

The project schedule runs from February 2022, when Phase I was approved, to December 2027. Phases I to III are already complete. Phase IV is due by 18 December 2027.

2. When did work on the project start?

Work on Phase I started on 3 March 2022, the same day the Joint Development Agreement was registered. Phase I is the largest phase, with 523 plots. It reached completion on 3 March 2025.

3. How long does each phase take to complete?

Phase I took about 36 months, while Phase II took about 33 months. Phase III ran for about 24 months. Phase IV is planned for about 20 months, from May 2026 to December 2027.

4. Why are the later phases faster?

Phases II and III are much smaller than Phase I, so they need less time. Each new phase also builds on the team's experience from earlier phases.

5. Is the Phase IV schedule on RERA?

Yes, Phase IV registered with Karnataka RERA in May 2026, with a completion date of 18 December 2027. You can check this on the RERA portal using the phase's registration number. The portal also shows progress filings.

6. Will the metro open before Phase IV completion?

The Hebbal to airport stretch of the Blue Line is targeted for June 2027. Phase IV is due by 18 December 2027. So the metro stretch is scheduled to open a few months before Phase IV completion.