Vaishnavi AT-One Life Project Schedule

Vaishnavi AT-One Life Project Schedule runs from February 2022 to December 2027 across four phases. Phase I began in March 2022 and reached completion in March 2025. Phases II and III followed, finishing in May 2025 and June 2026. Phase IV started on 1 May 2026 and has a RERA completion date of 18 December 2027.
This page lays out the full schedule in one place, from plan approval to completion for every phase. It also explains how long each phase took and what the schedule means for your buying plans.