Vaishnavi AT-One Life Completion Date

Featured Image of Vaishnavi AT-One Life Completion Date


Vaishnavi AT-One Life Completion Date for the full project is 18 December 2027, when Phase IV finishes. The first three phases are already complete. Phase I reached completion on 3 March 2025 and Phase II on 29 May 2025. Phase III followed on 5 June 2026. These dates come from the project's Karnataka RERA records.

This page explains the completion date of each phase and what "completion" covers in a plotted layout. It also shows how the group's delivery record helps you judge the Phase IV timeline.

Phase-Wise Completion Dates


Phase Plots Land Area RERA Completion Date Status
Phase I 523 39.12 acres 3 March 2025 Completed
Phase II 64 5.35 acres 29 May 2025 Completed
Phase III 85 5.77 acres 5 June 2026 Completed
Phase IV 227 16.12 acres 18 December 2027 Ongoing

With three phases done, 672 of the project's 899 plots now sit in completed parts of the layout. Phase IV will complete the full 66.36-acre project.

What Completion Covers in a Plotted Project


In a plotted project, completion means the layout is fully built, not the homes. The developer must finish the roads, drains, utility lines and open spaces within each phase. Once these works are done, plots are ready for registration and handover.

At Vaishnavi AT-One Life, the completion scope includes the following works:

  • Roads: tarred internal roads of 30 ft, 40 ft and 60 ft, with curbs and culverts.
  • Utilities: underground power cables, water lines and sewage lines for every plot.
  • Drainage: an underground drainage system and storm water pipe network.
  • Water systems: borewells, underground sumps, overhead tanks and treatment units.
  • Green spaces: parks and open spaces, which take about 10% of the land in each phase.
  • Safety: solar street lights, road and plot signage, a guard office and CCTV at key points.

After completion, you build your own home on your plot, based on your approved building plan.

Completion of Phase I


Phase I is the biggest phase, with 523 plots on 39.12 acres. Work began on 3 March 2022, and the phase reached its completion date on 3 March 2025. That is a planned build time of about three years.

Phase I includes 11 parks and 7 civic amenity sites. Since it is complete, it is the best place to judge the finished layout on your site visit.

Completion of Phases II and III


Phase II holds 64 plots on 5.35 acres and reached completion on 29 May 2025. Phase III holds 85 plots on 5.77 acres and reached completion on 5 June 2026. Both phases sit in Bettanahalli Village, next to Phase I.

These two smaller phases add to the plot choice in the completed part of the project. Phase II mostly offers 30x50 plots, while Phase III offers 30x40, 30x50 and odd-sized plots.

Phase IV Completion Date


Phase IV is the only phase still in progress. It covers 16.12 acres in Kamenahalli Village and holds 227 plots. Work started on 1 May 2026, and its RERA completion date is 18 December 2027.

Phase IV includes 8 parks and 2 civic amenity sites. About 52% of its land goes to plots, while roads take about a third. Once Phase IV is done, the whole Vaishnavi AT-One Life project will be complete.

The Developer's Delivery Record


A developer's past record is the best guide to future completion. Vaishnavi Group has now taken three phases of this project to completion. Each phase reached its RERA completion date as per the project's status.

The group also has a record outside this project. Its Vaishnavi Serene project in Yelahanka received its occupancy certificate five months ahead of schedule. This history gives buyers more confidence in the Phase IV date.

Why the Completion Date Matters to You


The completion date affects when you can register your plot and start building. It also shapes your payment plan, loan timing and moving plans.

If you want to build soon, pick a plot in Phases I to III. If you prefer to buy now and build in 2028, Phase IV gives you a clear end date. In both cases, check the RERA portal from time to time for progress updates.

It also helps to plan your home design while the layout is being finished. An architect can draw your plans in advance, so you can apply for approval soon after handover. This simple step can save you several months once your plot is ready.

FAQs


1. What is the completion date of Vaishnavi AT-One Life?

The full project is due to complete on 18 December 2027, when Phase IV finishes. Phases I, II and III are already complete. These dates come from the project's RERA records.

2. When did Phase I complete?

Phase I reached its completion date on 3 March 2025. It is the largest phase, with 523 plots on 39.12 acres. Work on this phase had started on 3 March 2022.

3. Are Phases II and III complete?

Yes, Phase II reached completion on 29 May 2025 and Phase III on 5 June 2026. Together they hold 149 plots in Bettanahalli Village. Both phases sit next to Phase I.

4. What is the Phase IV completion date?

Phase IV has a RERA completion date of 18 December 2027. It holds 227 plots on 16.12 acres in Kamenahalli Village. Work on Phase IV started on 1 May 2026.

5. What does completion mean for a plot?

Completion means the layout works are finished, including roads, drains, utility lines and parks. After this, plots are ready for registration and handover. You then build your own home on the plot.

6. Has Vaishnavi Group delivered on time before?

Vaishnavi Group has taken three phases of this project to completion. Its Vaishnavi Serene project in Yelahanka also received its occupancy certificate five months early. This record supports confidence in the Phase IV date.